Target Costing, Kaizen Costing and Just-in-Time

Three Japanese-inspired ways to manage cost: set cost from the market price, cut it a little every month, and remove the waste of stock.

Uses ideas from Variance Analysis. Which ideas

3 conceptsAbout 11 min
Start with the first concept
Part one

The concepts

Concept 1 of 3.

Target costing

Start from the price the market will pay and work back to cost.

Before you read

A mixer-grinder costs ₹2,650 to make. Rivals sell for ₹3,000, and the firm wants 20% profit on price. Should it raise its price or cut its cost?

Core idea

Target cost = selling price − desired profit. The price is fixed by the market, so the cost is the thing to change, and most of it is set in design.

Chennai Mixers has designed a mixer-grinder that costs ₹2,650 to make. Rivals sell similar ones for ₹3,000. Adding its usual 20% to cost gives ₹3,180, which no buyer will pay. Is the answer to lower the margin, or to lower the cost?

In plain wordsTarget costing starts from the price the market will pay, takes away the profit the firm wants, and treats what is left as the most the product may cost. The task is then to design the product to that cost.

Exam definitionTarget cost is a cost estimate derived by subtracting a desired profit margin from a competitive market price. Target costing is a management technique in which prices are set by market conditions and costs are planned and managed out of a product early, in design and development.

Target cost = Selling price − Desired profit

The mixer-grinder. Market price ₹3,000. Desired profit 20% of price = ₹600. Target cost = ₹3,000 − ₹600 = ₹2,400. The first design costs ₹2,650, so there is a gap of ₹250 to be designed out.

Cost-plus: start from costCost ₹2,650= ₹3,180Target costing: start from the market priceTarget cost ₹2,400+₹600Market price ₹3,000
Cost-plus prices a product from its cost and may land above what customers will pay. Target costing fixes the price first and treats the cost as the thing to change.
ActionSaving per unit
Redesign the casing and remove a part₹120
Renegotiate the motor price with the supplier₹80
Cut a step from assembly₹50
Total₹250

If the design could not be changed and the firm sold at ₹3,000, it would earn ₹350, which is only 11.7% of the price against the 20% wanted.

Why use it. When products are alike, competition is strong and customers switch easily, the firm cannot set the price, so it must control the cost. Most of a product’s cost is fixed at the design stage, so the saving must be sought there, not after production has begun.

StepWhat happens
1. Market researchLearn what customers want and what they will pay
2. Maximum costSet the profit margin and from it the highest allowable cost
3. Design the productEngineers and designers create it to that cost
4. Analysis and adjustmentCompare design cost with the target; redesign or cut costs if over
5. Design improvement and trialsTest features; continue until cost and customer needs are both met
6. Management approvalPresent the design, tests and cost to management
7. Record keepingKeep accounts to check costs stay within the target
8. ImplementationMake the product, and keep checking cost and quality

Objectives. To lower the cost of new products so that the required profit is ensured; to meet the quality, delivery time and price the market needs; and to make everyone in the firm responsible for the target profit.

Benefits. Better profit through lower cost, innovation shaped by what customers want, customer satisfaction, and a leaner production process.

Don’t confuse target costing with cost-plus pricing. Cost-plus starts with cost and adds profit to reach a price. Target costing starts with the price and takes profit away to reach a cost. The first lets inefficiency pass into the price; the second makes the cost bear the pressure of the market.

Where it breaks. A target set too hard may lead designers to cut quality or safety, or to push the cost onto suppliers who cannot bear it. A product with no real market price, such as a new invention, has nothing to start from. The work in design and testing adds cost of its own.

For exams. Know the formula, the contrast with cost-plus, the objectives, the steps and the benefits.

Price first, profit second, cost is what is left.

Go deeper for practitioners

Value engineering. The main tool for closing the gap is to study each part of the product for what it does for the customer and what it costs, then to remove features the customer does not value or to find a cheaper way to deliver the ones they do. Cost is taken out in design, not squeezed in the factory.

A decision. A target cost calls for dropping a feature that your sales team says some customers like. How would you decide whether to keep it?

Check yourself

1. The market price is ₹3,000 and the desired profit is 20% of price. The target cost is…

Not quite. The answer is “₹2,400”. 20% of ₹3,000 is ₹600, and ₹3,000 − ₹600 = ₹2,400.

2. The first design costs ₹2,650 against a target of ₹2,400. The cost gap to close is…

Not quite. The answer is “₹250”. ₹2,650 − ₹2,400 = ₹250 per unit.

3. How does target costing differ from cost-plus pricing?

Not quite. The answer is “It starts from the market price and works back to a cost”. Cost-plus starts from cost; target costing starts from price.

Reflect & discuss

“Think of a product you buy often. Which feature could its maker remove without you noticing, and what would that save?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
Target costing
  • Target cost = Selling price − Desired profit.
  • Price is set by the market, so cost is managed from the design stage.
  • Steps: research, maximum cost, design, adjust, improve, approve, record, implement.
  • Benefits: profit, innovation, customer satisfaction, efficient production.
Remember

Price first, profit second, cost is what is left.

Concept 2 of 3.

Kaizen costing

Continuous improvement, a little each month.

Before you read

A product launched at its target cost. A year later rivals have cut costs. What does the firm need?

Core idea

Kaizen is continuous improvement. Kaizen costing sets regular cost-reduction targets for existing products, reviews variances each period, and removes the seven wastes. It differs from re-engineering, which is a one-off radical change.

Chennai Mixers launches at the target cost of ₹2,400. A year later rivals have cut theirs. If cost stays still, the margin shrinks. Kaizen costing keeps cost falling by a little each month.

In plain wordsKaizen is the Japanese word for continuous improvement. Kaizen costing sets a small cost-reduction target each period for products already being made, and everyone looks for waste to remove.

Exam definitionKaizen costing is a system for continuing cost reduction of existing products and processes. Targets for cost reduction are set regularly, for example monthly, and variance analysis at the end of each period compares the target reduction with the actual. It focuses on cost reduction rather than cost control.

The mixer-grinder, month by month. The unit cost is ₹2,400. The target is to take ₹20 off every month.

MonthTarget unit costActual unit costVariance
1₹2,380₹2,385₹5 A
2₹2,360₹2,355₹5 F
3₹2,340₹2,345₹5 A
4₹2,320₹2,310₹10 F

In months 1 and 3 the firm fell short of its target and in months 2 and 4 it beat it. After four months the actual cost is ₹2,310, which is ₹90 below the start. The variance is a prompt to find which waste was removed, and which was not.

Continuous improvement, not re-engineering. Kaizen is small steps taken all the time by everyone. Business process re-engineering is a radical, one-off change. The thinking behind Kaizen is that perfection is never reached, so there is always something to improve, and that improvements from the people who do the work are usually small.

WasteWhat it means
Over-productionMaking more than customers have ordered
InventoryHolding or buying stock that is not needed
WaitingDelays and idle time that add no value
DefectsParts that are scrapped or must be reworked
MotionMovements of people or machines that add no value
TransportationMoving material or work-in-progress more than needed, because of poor layout
Over-processingSteps that add no value for the customer

Principles. It does not take the present situation as given. It seeks gradual improvements, not perfection at any cost. It allows managers to use their knowledge and discretion and encourages shared decision-making, on the view that many minds do better than one. Standards are set and then improved continually.

Don’t treat Kaizen as the same as standard costing. A standard cost is a fixed yardstick, and a variance is judged against it. In Kaizen costing the yardstick itself is lowered every period. Kaizen costing is about reducing the cost, while standard costing is about controlling it at the level set.

Where it breaks. Targets that keep falling can run out of room, and employees may feel pressure when no improvement is ever enough. Gains from small steps need a culture that rewards suggestions. Cutting cost without regard to quality can harm customers.

For exams. Give the meaning, the contrast with cost control and with re-engineering, the seven wastes and the principles.

Small cuts, every month, by everyone.

Go deeper for practitioners

Target costing and Kaizen together. Target costing fixes the cost at launch, through design. Kaizen costing then takes over for the life of the product, taking cost down in steps. Together they cover the whole life: design to the market price, then improve.

A decision. A supervisor reports she has met every Kaizen target for a year, but quality complaints have risen. What would you check, and what would you change about the targets?

Check yourself

1. Unit cost is ₹2,400 with a target of ₹20 off each month. The target for month 3 is…

Not quite. The answer is “₹2,340”. ₹2,400 − 3 × ₹20 = ₹2,340.

2. Which is one of the seven wastes?

Not quite. The answer is “Waiting and idle time”. The seven wastes are over-production, inventory, waiting, defects, motion, transportation and over-processing.

3. Kaizen costing focuses on…

Not quite. The answer is “Cost reduction rather than cost control”. Standard costing controls cost at a set level. Kaizen costing lowers the level continually.

Reflect & discuss

“What small improvement could you make this week in a routine task, and what waste would it remove?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
Kaizen costing
  • Kaizen: continuous improvement by everyone, in small steps.
  • Kaizen costing: regular cost-reduction targets and variance review.
  • Seven wastes: over-production, inventory, waiting, defects, motion, transportation, over-processing.
  • Different from re-engineering (radical) and from standard costing (fixed yardstick).
Remember

Small cuts, every month, by everyone.

Concept 3 of 3.

Just-in-time (JIT)

Inventory is waste.

Before you read

A firm holds ₹12,00,000 of stock at a 20% yearly carrying cost. What does holding it cost?

Core idea

JIT brings materials and parts exactly when needed and makes goods to order. Its slogan is ‘inventory is waste’. It grew at Toyota, and works in production, inventory, services and information.

Chennai Mixers holds about ₹12,00,000 of motors, castings and finished goods. At 20% a year for storage, insurance, interest and spoilage, holding it costs ₹2,40,000 a year. What if the goods arrived only when they were needed?

In plain wordsJust-in-time brings materials and parts exactly when the factory needs them, and makes goods only as customers order them. The idea is that stock is waste.

Exam definitionJust-in-time (JIT) is an inventory management method in which labour, materials and goods are re-filled or scheduled to arrive exactly when needed in the manufacturing process. Its philosophy is that inventory is waste. It stands for producing the required units, in the required quantities, at the required time.

The saving. Suppose JIT cuts the average stock from ₹12,00,000 to ₹3,00,000. Carrying cost falls from ₹2,40,000 to ₹60,000, a saving of ₹1,80,000 a year, and ₹9,00,000 of working capital is freed.

Where it came from. JIT was developed at Toyota, and Taiichi Ohno is usually called its father. It worked only because everyone was committed, the plant was laid out for efficient flow, and quality and production schedules matched demand.

Objective
Minimise the cost of production
Link suppliers with the manufacturer and save material and time
Improve processes and systems continuously
Reduce the cost of products and meet customer needs
Raise efficiency and cut waste in materials, time and effort
Reach the best balance of quality and cost
EnvironmentWhat it means
ProductionBuy, make, assemble and deliver each stage just in time for the next: ideally one unit in process and no finished stock
InventoryBuy materials just in time; make or assemble to order
ServicesSchedule trained service staff and tasks to fit the orders, ‘service to order’
InformationKeep the necessary information ready and up to date, linked with those who need it

JIT purchasing in steps. Find a reliable supplier. Work out the internal and external lead times. Prepare the bill of materials and the master production schedule against time. Order the items to arrive within the lead times. Move material straight to the shop floor, make or assemble to schedule, and deliver as planned. A small temporary store may be kept if needed. The aim is to remove the warehouse and its carrying cost.

Don’t think JIT only means less stock. JIT needs steady quality, short set-ups, reliable suppliers and a tight schedule. A firm that cuts stock without these simply runs out of parts. The stock was hiding problems, and JIT exposes them, so they must be solved.

Where it breaks. A supply failure stops the line at once, because there is no buffer. Heavy dependence on a few suppliers, long supply routes or sudden demand swings make JIT risky. Some firms now hold a safety stock of critical parts.

For exams. Know the meaning, the slogan ‘inventory is waste’, the origin, the objectives, the four environments and the steps of JIT purchasing.

The right unit, in the right quantity, at the right time.

Go deeper for practitioners

Why the three belong together. Target costing sets the cost at design. Kaizen costing reduces it continuously. JIT removes the waste of stock and waiting. All three treat waste as the enemy, and cost reduction as everyone’s job.

A decision. A firm wants to adopt JIT, but its main supplier is 600 km away and has twice been late. What would you do before cutting stock?

Check yourself

1. JIT cuts average stock from ₹12,00,000 to ₹3,00,000 at 20% carrying cost. The yearly saving is…

Not quite. The answer is “₹1,80,000”. Carrying cost falls from ₹2,40,000 to ₹60,000, a saving of ₹1,80,000. The ₹9,00,000 is the stock released.

2. The slogan of JIT is…

Not quite. The answer is “Inventory is waste”. JIT treats stock as a waste that hides problems.

3. A main risk of JIT is…

Not quite. The answer is “A supply failure stops production at once”. With no buffer stock, one late delivery halts the line.

Reflect & discuss

“What would you need to be sure of before cutting stock to almost nothing in a factory that depends on a distant supplier?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
Just-in-time (JIT)
  • JIT: the right unit, in the right quantity, at the right time.
  • Origin: Toyota; Taiichi Ohno.
  • Four environments: production, inventory, services, information.
  • Needs reliable suppliers, steady quality and tight schedules.
Remember

The right unit, in the right quantity, at the right time.

Test yourself

All 9 questions from this chapter, in a new order.

The ones you miss join your review, and come back until they stick.

Start the chapter test

How this chapter connects

Worked out from the glossary terms each chapter uses. A chapter is listed when two or more terms are shared.

Uses ideas from
Cite this page
  • APA

    Veda Verse. (2026, October 18). Target Costing, Kaizen Costing and Just-in-Time. https://myvedaverse.in/learn/target-costing-kaizen-costing-and-jit

  • MLA

    “Target Costing, Kaizen Costing and Just-in-Time.” Veda Verse, 18 Oct. 2026, myvedaverse.in/learn/target-costing-kaizen-costing-and-jit.

  • Chicago

    Veda Verse. “Target Costing, Kaizen Costing and Just-in-Time.” Last modified October 18, 2026. https://myvedaverse.in/learn/target-costing-kaizen-costing-and-jit.

Check the form your course asks for. The date is when this page's content last changed.