Activity-Based and Life-Cycle Costing

How ABC charges overhead by the activities that cause it, and how life-cycle costing counts the whole cost of a product or an asset.

Uses ideas from Cost Sheet and Product Decisions. Which ideas

3 conceptsAbout 11 min
Start with the first concept
Part one

The concepts

Concept 1 of 3.

Activity-based costing: the ideas

Pools, drivers and why volume alone can mislead.

Before you read

A factory sets up machines far more often for a low-volume custom product. Charged by labour hours, will that product look cheaper or dearer than it is?

Core idea

ABC traces costs to activities and then to products by cost drivers. The driver rate is the cost of the pool divided by the driver units. Drivers may be transaction, duration or intensity drivers.

A factory makes a standard gear in thousands and a custom gear in hundreds. Each month it sets up machines, inspects parts and orders material far more often for the custom gear. If overhead is shared by machine hours alone, the custom gear looks cheaper than it is.

In plain wordsActivity-based costing (ABC) charges overhead to products according to the activities each product causes, not just its volume. Costs are first traced to activities, then to products.

Exam definitionActivity-based costing is a system in which costs are first traced to activities and then to products, on the assumption that activities cause costs. Costs are charged to products according to each product’s use of each activity.

Resourcesrent, power,salaries, depreciationActivitiesset-ups, inspection,material handlingProductsor services,customers, jobsStage 1: assign costs to activity poolsStage 2: charge products by use (cost drivers)
Traditional costing goes from resources to products in one step, by volume. ABC goes via activities.
TermMeaningExample
Cost objectAnything for which a separate cost is wantedA product, service, project, customer or brand
Cost unitA unit of product, service or time for which cost is statedKilowatt-hour for a power firm
ActivityA group of tasks tied to a cost objectScheduling, set-ups, purchasing, inspecting
Cost poolA group of indirect costs with similar behaviour, one for each activityAll set-up costs together
Cost driverThe factor that causes the cost of an activityNumber of set-ups, kilometres run
Cost driver rateCost of the pool ÷ number of driver units₹6,000 a set-up

Three kinds of driver. A transaction driver counts how many times an activity is done (orders, inspections, set-ups). A duration driver counts the time it takes (set-up hours, inspection hours). An intensity driver charges directly for the resources used each time, for example a special inspection that uses an expensive tester.

BasisTraditional costingActivity-based costing
Cost flowsResources → departments → productsResources → activities → products
Base for overheadUsually volume: labour or machine hoursMany drivers, one for each activity
Cause and effectWeakDirect, by activity
Best suited toFew products, low overheadMany products, and overhead a large share of cost

Don’t confuse a cost pool with a cost driver. The pool is the money: all the set-up costs added together. The driver is the cause you divide it by: the number of set-ups. The pool divided by the driver units gives the rate.

Where it breaks. ABC needs good data and takes effort to set up, and the choice of activities and drivers is a judgement. Facility-level costs, such as the factory building, have no real driver, and any rule for sharing them is arbitrary. A firm with one product gains little.

For exams. Know the six terms, the three kinds of driver, the features of ABC and the comparison with traditional costing.

Activities cause costs; products use activities.

Go deeper for practitioners

Why overhead has grown. In a firm of the past, labour was most of the cost, so labour hours were a fair base. In a modern plant, machines, planning, quality checks and design are a large part of cost, and they do not rise with labour hours. That is why ABC became useful as overhead became a bigger share of cost.

A decision. A bank branch charges every customer the same overhead per account. Which customers would ABC show to be costing more than they pay, and what could the bank do about it?

Check yourself

1. A set-up pool costs ₹2,40,000 and there are 40 set-ups. The cost driver rate is…

Not quite. The answer is “₹6,000 a set-up”. ₹2,40,000 ÷ 40 = ₹6,000. The pool is the money; the driver units are the 40 set-ups.

2. Counting the number of inspections performed uses which kind of driver?

Not quite. The answer is “A transaction driver”. A transaction driver counts how many times an activity is done. A duration driver counts the time it takes.

3. ABC is most useful when…

Not quite. The answer is “There are many products and overhead is a large share of cost”. With one product and little overhead, the way overhead is shared barely matters.

Reflect & discuss

“Think of a restaurant with a few dishes that need much more preparation than others. What would an activity-based view say about the price of those dishes?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
Activity-based costing: the ideas
  • ABC: resources → activities → products, by cost drivers.
  • Cost pool: indirect costs with similar behaviour. Cost driver: the cause of the cost.
  • Driver rate = Pool cost ÷ Driver units.
  • Drivers: transaction (count), duration (time), intensity (direct charge).
Remember

Activities cause costs; products use activities.

Concept 2 of 3.

The steps of ABC and a worked example

Four steps and four levels, worked on Hosur Gears.

Before you read

ABC and traditional costing both share ₹6,00,000 of overhead between two products. Does ABC change the total?

Core idea

The steps are: identify activities, assign costs to pools, select drivers, and charge products by use. The levels are unit, batch, product and facility. For Hosur Gears, the custom gear’s overhead is ₹296 a unit under ABC against ₹120 traditionally.

Hosur Gears makes 8,000 standard gears and 1,000 custom gears with ₹6,00,000 of overhead. Charged by labour hours, the custom gear carries ₹120 of overhead. What does it actually cost to make?

In plain wordsABC works in four steps: identify the activities, put their costs in pools, choose a driver for each pool, and charge each product for what it uses.

Exam definitionThe steps in an ABC system are: identifying activities; assigning costs to activity cost centres (cost pools); selecting appropriate cost drivers; and assigning the cost of the activities to products according to each product’s demand for the activities.

Four levels of activity (Cooper and Kaplan). Unit-level activities occur with every unit made (machining, testing each item). Batch-level activities occur once per batch (ordering, set-ups, inspecting a lot). Product-level activities support a product line (design, drawings, product advertising). Facility-level activities support the whole plant (building upkeep, security, the plant manager’s salary). ABC matters most when batch and product-level costs are a big share of the total.

Standard gearCustom gearTotal
Units made8,0001,0009,000
Direct labour hours8,0002,00010,000
Batches (set-ups)103040
Inspections206080
Activity poolCostDriverDriver unitsRate
Set-ups₹2,40,000Batches40₹6,000 a batch
Inspection₹80,000Inspections80₹1,000 each
General factory₹2,80,000Labour hours10,000₹28 an hour
Total₹6,00,000
Standard gearCustom gear
Set-ups₹60,000₹1,80,000
Inspection₹20,000₹60,000
General factory₹2,24,000₹56,000
ABC overhead₹3,04,000₹2,96,000
ABC overhead per unit₹38₹296
Traditional overhead at ₹60 a labour hour₹4,80,000₹1,20,000
Traditional overhead per unit₹60₹120

Traditional costing gives the custom gear ₹120 of overhead a unit, and ABC gives it ₹296. The standard gear is the other way round: ₹60 against ₹38. If the custom gear sells for ₹300 and has ₹100 of direct cost, traditional costing shows a profit of ₹80 a unit and ABC shows a loss of ₹96. The standard gear has been paying for part of the custom gear’s complexity.

Don’t think ABC creates cost. The total overhead, ₹6,00,000, is the same under both methods: ₹4,80,000 + ₹1,20,000 against ₹3,04,000 + ₹2,96,000. ABC only shares it differently, by cause. Only the split between products changes.

Where it breaks. The result depends on the pools and drivers chosen. Too few pools return to the traditional answer, and too many cost more to run than they are worth. Unit-level and facility-level costs are still shared on volume. A price rise alone may not be the right response to a loss on a product; redesign or fewer set-ups may be better.

For exams. Show the pools, the driver rates, the charge to each product and the comparison with the traditional method.

Pool the cost, find the driver, charge by use.

Go deeper for practitioners

What management can do. The ABC figures point to actions: cut the number of set-ups by making longer runs, simplify the custom gear, or price it to cover its true cost. Many firms use ABC for pricing, product-mix and cost-reduction choices rather than for the formal accounts.

A decision. Hosur’s customers for the custom gear say they will leave if the price rises to ₹420. Using ABC, what would you propose to keep them and stay profitable?

Check yourself

1. A product has 30 batches and the set-up rate is ₹6,000 a batch. Its set-up cost is…

Not quite. The answer is “₹1,80,000”. 30 × ₹6,000 = ₹1,80,000. ₹2,40,000 is the pool for all products.

2. Which is a batch-level activity?

Not quite. The answer is “Machine set-up”. A set-up occurs once per batch. Machining each unit is unit-level, designing is product-level and security is facility-level.

3. The custom gear sells for ₹300 and has ₹100 of direct cost and ₹296 of ABC overhead per unit. Its profit per unit is…

Not quite. The answer is “A loss of ₹96”. ₹300 − ₹100 − ₹296 = −₹96. Traditional costing, with ₹120 of overhead, would have shown a profit of ₹80.

Reflect & discuss

“If ABC shows a product loses money, what could you do besides raising its price?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
The steps of ABC and a worked example
  • Four steps: identify activities; pool costs; choose drivers; charge products.
  • Four levels: unit, batch, product, facility.
  • ABC changes the split of overhead, not the total.
  • Facility-level costs still have no true driver.
Remember

Pool the cost, find the driver, charge by use.

Concept 3 of 3.

Life-cycle costing

The cost of owning, not just the cost of buying.

Before you read

Machine Y costs ₹3,00,000 less than Machine X but costs more each year to run. Is Y the cheaper machine?

Core idea

Life-cycle costing adds every cost from first idea to disposal, usually discounted. Product life-cycle costing covers a product in the market; project (whole-life) costing covers a physical asset.

A hospital can buy a scanner for ₹70 lakh or for ₹1 crore. The cheaper one costs more to run and repair. Which is better? The purchase price is only one part of what an asset costs over its whole life.

In plain wordsLife-cycle costing adds every cost of a product or an asset from its first idea to its disposal, so choices are judged on the whole life and not just the price on the day.

Exam definitionLife-cycle costing is a system that tracks and accumulates the actual costs and revenues attributable to a cost object from its invention to its abandonment. Life cycle cost is the total cost of ownership: the cost to acquire, operate, support and finally dispose of an item, usually discounted to a common basis.

Product life-cycle costingProject (whole-life) costing
ConcernsA product or service in the marketA physical asset or project
Starts atIdentifying a customer needFeasibility study and acquisition
IncludesResearch, design, development, tooling, making, selling, distribution, product support, withdrawalPurchase, transport, installation, running, energy, maintenance, training, spare parts, retirement and disposal
Used toSee the long-term profit of a product against the early costs of design and launchChoose between assets and plan budgets

Stages of a product’s life. Market research, specification, design, prototype, development, tooling, manufacture, selling, distribution, product support, and decommissioning. Much of the cost is fixed in design, long before production begins.

Characteristics. It traces costs and revenues over several periods. It compares design and development costs with the revenue of the product. Each phase brings its own threats and opportunities. The life of a product can sometimes be extended by finding new users or new uses.

Choosing a machine. Machine X costs ₹10,00,000 and runs and is maintained for ₹1,50,000 a year. Machine Y costs ₹7,00,000 and costs ₹2,50,000 a year to run. Each lasts 5 years and then sells for ₹1,00,000 (X) or ₹50,000 (Y). The firm discounts at 10%, with running costs at each year-end.

Machine XMachine Y
Purchase price₹10,00,000₹7,00,000
Running costs over 5 years (undiscounted)₹7,50,000₹12,50,000
Less: sale at the end−₹1,00,000−₹50,000
Life-cycle cost, undiscounted₹16,50,000₹19,00,000
Life-cycle cost, discounted at 10%₹15,06,526₹16,16,651

Machine Y is ₹3,00,000 cheaper to buy, but over its life it costs about ₹1,10,125 more in present-value terms. The discounted figures use an annuity factor of 3.7908 for the running costs and 0.6209 for the sale in year 5.

Don’t decide on purchase price alone. Using the price alone overstates the return on the cheaper asset and understates the budget needed to run it. A budget that leaves out future running costs makes profit look larger than it will be.

Where it breaks. Future costs, lives and sale values are estimates, and the answer can flip if the discount rate or life changes. Benefits are not always the same for each choice, so cost alone may not be the test. Costs such as downtime or disposal rules are easy to overlook.

For exams. Know the two types, the stages of a product’s life, the heads of whole-life cost, and the three purposes: choose between assets, judge benefits and build accurate budgets.

Count the cost of owning, not just the cost of buying.

Go deeper for practitioners

Design decides cost. The largest part of a product’s lifetime cost is usually committed at the design stage, even though most of it is spent later. That is why life-cycle costing pushes cost thinking back into design and specification, where changes are cheap.

A decision. A municipality can buy a ₹20 lakh diesel bus or a ₹30 lakh electric bus. List the life-cycle cost heads you would estimate for each, and say which estimate you trust least.

Check yourself

1. Machine X: price ₹10,00,000, running ₹1,50,000 a year for 5 years, sale ₹1,00,000. Undiscounted life-cycle cost is…

Not quite. The answer is “₹16,50,000”. ₹10,00,000 + ₹7,50,000 − ₹1,00,000 = ₹16,50,000. The sale at the end reduces the cost.

2. Project life-cycle costing is about…

Not quite. The answer is “Acquiring, using, maintaining and disposing of a physical asset”. It covers all the costs of an asset from purchase to disposal.

3. Most of a product’s lifetime cost is committed at which stage?

Not quite. The answer is “Design”. Design and specification fix most of the later costs, even though they are spent later.

Reflect & discuss

“Think of something you bought mainly on price. What running or disposal costs did you not count at the time?”

Kept on this device. Nobody sees it unless you share it.

Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.

One-page summary
Life-cycle costing
  • Life cycle cost = acquire + operate + support + dispose, usually discounted.
  • Product LCC: research to withdrawal. Project LCC: purchase to disposal of an asset.
  • Uses: choose between assets, judge benefits, build accurate budgets.
  • The cheapest asset to buy is not always the cheapest to own.
Remember

Count the cost of owning, not just the cost of buying.

Test yourself

All 9 questions from this chapter, in a new order.

The ones you miss join your review, and come back until they stick.

Start the chapter test

How this chapter connects

Worked out from the glossary terms each chapter uses. A chapter is listed when two or more terms are shared.

Uses ideas from
Cite this page
  • APA

    Veda Verse. (2026, October 18). Activity-Based and Life-Cycle Costing. https://myvedaverse.in/learn/activity-based-and-life-cycle-costing

  • MLA

    “Activity-Based and Life-Cycle Costing.” Veda Verse, 18 Oct. 2026, myvedaverse.in/learn/activity-based-and-life-cycle-costing.