Standard costing and variances
A yardstick for cost, and the gaps that show where to look.
A plant spent ₹6,04,850 against a standard cost of ₹5,58,000 for the output it made. Is knowing the ₹46,850 gap enough?
Standard costing compares predetermined costs with actual costs. Variance = Standard − Actual; favourable if actual is less, adverse if more. Each total variance is the sum of its parts.
The standard cost of the 900 utensils Salem Steel Utensils made was ₹5,58,000. It actually spent ₹6,04,850. That is ₹46,850 over. A manager needs to know where the money went, not only that it went.
In plain wordsStandard costing sets what a unit should cost under good working conditions, then compares it with what it did cost. Each gap is a variance, and each variance points to a cause to look into.
Exam definitionStandard costing is a control technique that compares predetermined (standard) costs with actual costs to identify variances, analyse their causes and take corrective action. Variance = Standard cost − Actual cost; favourable (F) when standard exceeds actual, adverse (A) when standard is less than actual.
| Element | Quantity | Rate | Standard cost |
|---|---|---|---|
| Material | 4 kg | ₹50 | ₹200 |
| Labour | 3 hours | ₹80 | ₹240 |
| Variable overhead | 3 hours | ₹20 | ₹60 |
| Fixed overhead | 3 hours | ₹40 (₹1,20,000 ÷ 3,000 hours) | ₹120 |
| Standard cost | ₹620 |
The steps. Set the standard, measure the actual cost, compare the two, identify the variances and their causes, and report and act on them.
The sign. This chapter follows the usual rule: a variance is favourable when the actual cost is less than the standard, and adverse when it is more. In the tables that follow, F means a gain and A a loss.
Don’t compare actual cost with the budget for a different output. Salem’s standards are set for one utensil. The standard cost of the 900 actually made is the yardstick, not the cost of the 1,000 budgeted. Comparing with the budgeted output mixes a volume effect into every variance.
Where it breaks. Standards are estimates, and can be set too loose (easy to beat) or too tight (always missed). If prices are rising fast, the standards go out of date. A variance is a question, not a verdict: an adverse usage variance may come from poor material, not poor work.
For exams. Know the order of the steps, the sign convention, and the four total-variance identities.
Set, measure, compare, find the cause, act.
Go deeper for practitioners
Who owns a variance? A price variance on material is usually the buyer’s, a usage variance the production manager’s, a rate variance the HR or union agreement, and an efficiency variance the supervisor’s. Assigning each to an owner is what makes the system a control, not just a calculation.
A decision. A purchasing manager buys cheaper steel and the material price variance is favourable. The production manager complains of an adverse usage variance. How would you decide whether the saving was real?
1. The standard cost of the actual output is ₹5,58,000 and the actual cost is ₹6,04,850. The total variance is…
Not quite. The answer is “₹46,850 adverse”. Standard is less than actual, so the variance is adverse by ₹6,04,850 − ₹5,58,000 = ₹46,850.
2. Which is the correct order of steps in standard costing?
Not quite. The answer is “Set the standard, measure actual, compare, find the causes, act”. A standard must exist before actual cost can be compared with it, and action follows analysis.
3. Standard cost is the yardstick for…
Not quite. The answer is “The output actually made”. Comparing with a budget for a different output mixes a volume effect into every variance.
“Think of a household budget for groceries. Which gap would be a price variance and which a usage variance?”
Still unsure, or see it differently? Ask the community about thisYou’ll sign in first if you haven’t. Your note above stays private.
- Standard cost: predetermined cost under good conditions.
- Variance = Standard cost − Actual cost; F if actual is lower, A if higher.
- MCV = MPV + MUV; LCV = LRV + LEV + LITV; VOCV = VOEV + VOEEV; FOCV = FOEV + FOVV.
- A variance is a question to investigate, not a verdict.
Set, measure, compare, find the cause, act.